Hilltop Plat Information
Hilltop Plat Update (Tipp City)
The Hilltop Sewer Replacement and Storm Sewer Separation Project has been awarded to Associated Excavating Inc. of Brookville, Ohio. This project will replace a failed combined sewer system in the Hilltop Plat located south of Tipp City. Construction on this project should be starting by the end of January. A construction schedule will be forth coming. Substantial completion of this project is early spring.
We apologize for the mess and inconvenience of the construction projects. The cost and effort will pay off as the environment and our drinking water will be clean and clear. We appreciate all of your cooperation.
![]()
More information on Free Internal Wastewater Piping Evaluation for Hilltop Residents
![]()
Notice to all Hilltop Residents
The Hilltop project has been delayed one week and will begin on March 1st with clearing and grubbing.
Thanks,
Miami County Sanitary Engineering
937-440-5654
![]()
February 10, 2010
Re: Hilltop Subdivision Utility Extension Project
Dear Residents,
The Hilltop Subdivision Utility Extension Project has been awarded to Associated Excavating, Inc. Brookville, Ohio. The project is scheduled to start the week of February 22nd with Clearing and Grubbing of the easement areas. The contractor will also be doing layout and staking of the job. Pipe placement will begin the week of March 1st. The project is scheduled to be completed by the end of April.
I have attached a plan sheet showing where on your property the work will be completed. Lateral stakes will be placed to show where your lateral will be tied in. If the lateral location needs to be moved please let the inspector or contractor know so it can be moved to access your sewer outlet.
The inspector for this job is Dan Suerdieck and the Contractor is Mike Greer. If you should have any questions please contact me at 937-440-5654.
Jeff Shields, Superintendent