North County Road 25-A

 

The N. CR 25-A Sewer Extension Project has been awarded to Star Excavating Inc. of Covington, Ohio. This project is the third phase of a sewer extension project along North County Road 25-A just north of Troy.  The project has started with dewatering and the installation of a 96’ eight inch pipe bored under CR 25-A.  The installation of an eight inch (8”) sewer main line will start on the east side of CR 25-A in the next week and continue for the next two months.  This line will head south along the east side of CR 25-A.  The east lane of the Northbound lane of CR 25-A will be closed during this portion of the project.  Once this line is complete the project will then proceed to the installation of an eight inch (8”) sewer along the east side of Harrison Street.   Substantial completion for the project is early spring.